Use the full checklist below or download the fillable pack. Supply a separate record for each different load, crane or rigging arrangement. Mark unknown information clearly; use N/A with a reason where an item does not apply.
Project scope and responsibilities
Complete for each site or distinct package of work. Tell us whether you need planning support only or a separately agreed wider service.
- Client and site organisations
- Client, principal contractor, site operator, crane supplier and contracting entity. Give the billing address and procurement contact.
- Planning contacts
- Name, company, phone and email for the appointed person, site manager, lifting supervisor, engineering reviewer and client approver. Identify any role still to be appointed.
- Scope requested
- State whether you require crane selection, calculations, 3D model, site visit, drawings, method statement, risk assessment, review of an existing plan or assistance with revisions.
- Type and complexity of operation
- Single crane, tandem or multiple crane, upending, pick and carry, unloading, demolition, repetitive lifting, confined space or another specialist operation. Identify critical lift rules used by the site.
- Responsibility and contract arrangement
- Crane hire or contract lift? Identify who appoints the planner, controls the operation, supplies verified site/load data, approves the plan and provides supervision. Attach the written allocation of responsibilities.
- Timing and interfaces
- Shutdown windows, shifts, delivery dates, simultaneous operations, site induction, review turnaround and permissions needed before work starts.
Do not assume that buying a drawing transfers lifting responsibilities. Under a crane hire arrangement, planning and execution responsibilities must be explicitly allocated; a contract lift arrangement must state what the supplier takes on. [2]
Load information for each item
Copy this page for every distinct load. Use a unique load ID and attach the manufacturer or fabricator drawing, lifting instructions and recent photographs.
- Identification and quantity
- Load ID, description, manufacturer, model, serial number if applicable, number of identical items and whether the item is new, used, damaged or modified.
- Verified lifted mass
- State mass in kg or tonnes, its source, date and uncertainty. Include contents, trapped liquids, insulation, attachments, temporary steelwork and loose parts. Identify separately what is excluded.
- Dimensions and orientation
- Overall length, width, height and diameter as relevant. Include protrusions, lifting and transport orientations, installation tolerances and any packaging or supporting frame.
- Centre of gravity
- Give the centre of gravity in three axes from an identified datum, with drawing and tolerance. Describe uneven, moving or liquid contents and changes during rotation or installation.
- Lifting points and structural suitability
- Show each lug/trunnion/pick point location and allowable load/direction. Supply design verification, material/weld information, inspection/NDT evidence and permitted sling angles where required.
- Load condition and handling limits
- Fragility, sharp edges, surface protection, no-clamp/no-sling zones, temperature, chemical contamination, pressure or hazardous contents. State wind-exposed area and restrictions from the manufacturer.
A mass entered in CAD is not weighing evidence. If mass, centre of gravity or lifting-point capacity is uncertain, describe the proposed verification method and responsible supplier. Do not substitute an unsupported estimate for a verified value.
Site survey and lifting geometry
Provide a current measured site plan. Mark a common horizontal and vertical datum so load, crane, structures and levels can be matched.
- Location and survey basis
- Address, coordinates, coordinate system, north direction, scale, survey date, drawing revision and survey accuracy. Identify whether dimensions were surveyed, measured, estimated or taken from mapping.
- Crane setup positions
- Mark crane centre of slew, orientation, outrigger or track footprint and setup levels. Show possible alternative positions, assembly area and counterweight/ballast tail-swing clearance.
- Pick and landing positions
- For each load ID, mark start/end coordinates, support levels, final elevation and orientation. Show the load centre of gravity and the intended hook line at pick and set.
- Travel path and worst positions
- Show the full slewing/load path and any change of radius, height or orientation. Include obstructions, required separation, intermediate holds and the most restrictive point.
- Heights and clearances
- Give rack/building/pipe/structure heights, load underside and top levels, hook height, rigging headroom and available boom/head clearance. Include deflection or movement allowances required by the responsible designer.
- Photographs and model files
- Supply views from the proposed crane position, pick point, landing point and approaches. Provide dimensioned PDF and native CAD/BIM or point-cloud files where available, with units and revision.
Map imagery is a location reference, not a dimensional survey. Mark what exists now and what will change before the lift. Include pipe racks and nearby operating plant, not only the crane and load.
Crane duty and configuration
Complete for every crane. If a crane has not been selected, name the supplier and describe the constraints so selection can be included in the agreed scope.
- Crane identity and supplier
- Manufacturer, full model/variant, fleet or serial number, year if relevant, crane owner contact and current manufacturer operating instructions.
- Selected duty chart
- Supply the exact chart or OEM planning output for the proposed configuration. Include chart reference/revision, units, working sector, radius, boom length and rated capacity at every governing stage.
- Boom and attachments
- Main boom length and telescoping mode, lattice sections, fly/jib type and length, offset/luffing angle, mast, derrick, superlift and any erected or stowed attachments.
- Ballast and support geometry
- Upper and lower counterweight masses, ballast/superlift radius, tray/trolley arrangement, outrigger extensions including asymmetry, track extension, support footprint and permitted level tolerance.
- Hoist and hook arrangement
- Hook block/ball or lifting attachment identity, mass and capacity; parts of line, rope/hoist limitations, auxiliary head and unused attachments. Supply all chart-required capacity deductions.
- Operating restrictions and reactions
- Manufacturer wind/load-area limits, permitted travel or pick-and-carry duty, slew restrictions, assembly procedure and maximum support reactions for the full operation. Include supporting output and input settings.
A crane brochure maximum capacity is not the selected duty. Gross suspended load and capacity deductions must follow the exact manufacturer chart convention so hook, accessories and attachments are neither omitted nor counted twice.
Rigging and tackle information
Provide a proposed tackle sketch and a rigging list, or ask LPP to develop the arrangement. Record actual items and manufacturer data before final verification.
- Load connections and arrangement
- Identify every lifting point and connection from crane hook to load. State direct attachment, basket, single/double-wrap choker or other hitch; show wrap locations, spacing and protection.
- Slings and leg geometry
- For each leg: ID, type/material, manufacturer, length and definition of length, WLL, condition, hitch, angle to vertical or included angle, adjustment range and any unequal lengths.
- Shackles and connection hardware
- IDs, type, WLL, pin diameter, internal dimensions, orientation and quantity. Include master links, swivels, hooks, lifting eyes, chain adjusters, clamps and manufacturer side-loading restrictions.
- Beams frames and special devices
- Spreader/lifting beam identity, self-weight, span, rated configuration, connection geometry, design/certification, examination and instructions. Include lifting frames, magnets or vacuum devices where applicable.
- Certificates and reductions
- Provide current thorough examination reports, inspection status and applicable instructions. Identify hitch/angle/bend-radius/temperature/edge reductions and permitted point loads. Do not apply a generic reduction without its basis.
- Fit and removal
- Show physical fit at hook, lugs and shackles; retained pins/latches, sling bearing surfaces and anti-slip measures. Explain how rigging will be installed and removed safely at pick and landing.
List each accessory mass separately for the suspended-load calculation. A 3D sling that visually reaches a point does not establish suitable length, capacity or connection fit.
Ground slabs and support design
Ask the site owner and the relevant geotechnical/structural designer to provide evidence for every crane support position, assembly area and travel route.
- Ground and surface description
- Soil, fill, hardstanding, concrete slab, suspended slab or other support. Include levels, gradients, drainage, recent works, deterioration, waterlogging and changes expected before the lift.
- Geotechnical evidence
- Ground investigation, formation details, allowable bearing pressure with units and basis, settlement limits, groundwater and restrictions. Name the competent person accepting the ground design.
- Concrete and buried structures
- Slab thickness, reinforcement, concrete strength, joints, edges, foundations, basements, culverts and buried tanks. Provide structural capacity evidence; identify punching, bending and load-spreading checks required.
- Underground services and nearby edges
- Current utility survey, service protection and exclusion distances; excavations, trenches, retaining walls, slopes, voids and backfilled areas. Show these against each support and the travel route.
- Crane reactions and load cases
- Supply manufacturer/supplier support reactions for the exact duty and governing slew/load positions. Identify units, static/dynamic/design factors, load cases and the highest reaction at each support.
- Mats pads and foundations
- Quantity, length, width, thickness, material, structural rating and layout. Supply mat/foundation calculations and evidence for effective contact area, support stiffness, bearing and settlement acceptance.
Concrete surface alone does not prove capacity. Do not divide total crane weight equally between supports. Bearing pressure uses a justified governing reaction and effective area; mat strength, slab and underlying ground still need checking separately.
Access hazards and site controls
Describe the conditions the lifting team will actually encounter, including delivery, crane assembly and dismantling.
- Vehicle route and access
- Gate widths/heights, road and bridge limits, turning space, gradients, overhead restrictions, delivery vehicle size, escort needs, unloading area and ground capacity on approach routes.
- Overhead and underground services
- Electricity lines, substations, cables, gas/water/process lines and utilities. Provide asset-owner requirements, isolation arrangements and agreed clearance controls; do not infer safe distances from a photograph.
- Operating plant and public interfaces
- Live process plant, pipe racks, occupied buildings, roads, railways, public boundaries and adjacent contractors. Identify shutdowns, exclusion zones, barriers, traffic diversions and interface owners.
- Environmental limits
- Expected wind and gust conditions at load/boom height, load sail area, lightning, visibility, lighting, rain, ice and temperature. Provide site and manufacturer stop/restart limits and monitoring arrangements.
- Special hazards and permits
- Hazardous areas, flammable/toxic materials, asbestos, contamination, confined spaces, work at height, hot work, excavation or road/rail permits. Attach relevant permits and site emergency requirements.
- People and emergency access
- Pedestrian routes, muster points, first aid, emergency contacts, rescue/access arrangements, exclusion-zone control and how the operation will stop and be made safe if conditions change.
Declare restrictions even if you expect another contractor to manage them. Name the owner of each isolation, permit and boundary control.
Method sequence and supervision
Supply the intended work sequence and site arrangements. Identify where the operation must pause for a check or authorisation.
- Preparation and assembly
- Delivery, unloading, crane positioning, support preparation, ballast/boom assembly, rigging installation, checks, permits, briefings and exclusion-zone setup.
- Lift sequence
- Describe attachment, taking the weight, initial balance check, hoisting, slewing/travelling, clearance checks, positioning, landing, securing and detaching. Identify intermediate hold points.
- Load stability and landing
- State how swing, rotation or sliding is controlled; tag-line arrangements and safe positions. Explain temporary supports, final fixings and how stability is confirmed before releasing the crane.
- Communication and visibility
- Signal method, radio channel and backup, lead signaller, blind zones, camera/spotter needs, language requirements and the agreed stop command.
- Personnel and competence
- Named appointed person/planner, supervisor, operators, slinger/signallers and specialist support. Supply role-specific competence evidence and arrangements for substitutes or shift changes.
- Failure and change control
- Actions for unexpected movement, loss of communication, equipment fault, wind increase or emergency. Who can stop/restart? Who reviews a change in load, crane, rigging, ground or sequence?
The plan must cover the full operation and allocate responsibilities. Planning detail and supervision should match the risks and complexity; complex lifts need appropriately competent planning. [1]
Tandem lifting and upending
Complete when two or more cranes/hoists share a load, a load is tailed or rotated, or the centre of gravity/load share changes. Otherwise mark N/A.
- Equipment and roles
- Identify each crane/hoist, main and tailing roles, operator positions, lead lifting supervisor and the specialist designer/reviewer.
- Geometry through every stage
- Attach stage drawings showing each crane position, hook coordinates, radii, load orientation, centre of gravity and attachment points from initial pick to final support.
- Load sharing and uncertainty
- Supply calculated share at each stage, unequal movement effects, centre-of-gravity tolerance, flexibility and load-transfer assumptions. Identify how share will be monitored or verified.
- Capacity and reactions by stage
- Provide each crane duty, suspended rigging/hook allowances, governing utilisation, support reactions and applicable manufacturer restrictions or agreed engineering factors.
- Synchronisation and tolerances
- Command hierarchy, communication, lift speeds, permissible differential hook movement, allowed tilt, hold points, separation and boom/rope/load collision controls.
- Transfer release and contingency
- Sequence for tailing/transfer, unloading an attachment, securing the final position and disconnecting. Describe credible failure/imbalance cases and the agreed safe response.
Do not assume a 50/50 load split or apply an arbitrary extra percentage. The load distribution and operating allowances need an engineering basis for the actual geometry and sequence.
Special operations and evidence
Identify additional requirements at enquiry stage so specialist input, time and cost can be agreed. This checklist does not make every operation suitable for acceptance.
- Travel tower and fixed equipment
- Pick-and-carry route/duty, gradients and tyre/track settings; tower/fixed crane foundations, ties, climbing and erection data; assembly/disassembly lifts and supporting plant.
- Marine offshore and floating work
- Vessel/barge stability, mooring, sea state, tidal levels, vessel motions, dynamic load basis, deck capacity and marine authority/operator requirements.
- Persons and confined access
- Any lifting of people, personnel carrier, work at height, confined-space entry or rescue requirement. Supply purpose, equipment suitability and specialist safe-system arrangements.
- Demolition extraction and uncertain loads
- Breakout/adhesion, embedded or seized parts, cutting sequence, structural instability, residual contents and how the load is made free. State how mass and load path will be verified.
- Temporary works and specialist design
- Engineered lifting points, beams, stools, grillage, mats, foundations, temporary bracing or transport frames. Identify designer, checker, design brief and approval interface.
- Standards and acceptance criteria
- Site procedures, applicable legislation/jurisdiction, relevant crane/rigging standards, critical-lift criteria, review category, independent check requirements and required document templates.
Tell us what you do not know. Specialist verification, surveys and site attendance are included only where agreed in the written scope; they are not automatically covered by ordering a lift-plan drawing.
Deliverables and supporting files
Agree the required outputs and submit current source documents with a clear filename, document number and revision. A marked-up attachment may answer several fields.
- Drawings and model outputs
- Select: site/plot plan, crane footprint, side elevation, tackle sketch, lift-path stages, 3D views/model, simulation, transport/setup layout. State paper sizes, scales, dimensions, CAD/BIM formats and project title block.
- Calculations and written pack
- Select: duty selection/utilisation, gross suspended load, rigging, clearance, ground/support checks, risk assessment, method statement, inspection checklist, briefing/sign-off sheets. Identify calculations by others.
- Minimum load and site attachments
- Load schedule; weight/centre-of-gravity evidence; lifting-point drawings; photos; measured site plan/elevations; services survey; pick/landing coordinates and levels; access and obstruction details.
- Crane rigging and ground attachments
- Exact duty chart/OEM output; configuration and hook data; support reactions; rigging list/certificates/instructions; ground report; slab drawings; mat/foundation data and engineering acceptance.
- Management and approval attachments
- Site rules; permit requirements; role/competence details; existing plan if revised; relevant inspection/examination records; emergency arrangements; client standards and approval process.
- File register and transfer
- List filename/document ID, revision, date and which question it answers. For large or sensitive models, request an agreed secure transfer route; do not send account passwords or access tokens.
Use the open-items register on the next page for anything missing. Provide native files where available as well as readable PDF copies. All dimensions need units and all geometry needs a common datum.
Open items and information handover
List unresolved evidence and changes so they remain visible. Copy this page as needed. A blank response does not mean that an item has been verified.
- Open item one
- Question/load ID; missing fact or evidence; person/company responsible; due date; impact on planning; document reference when closed.
- Open item two
- Question/load ID; missing fact or evidence; person/company responsible; due date; impact on planning; document reference when closed.
- Open item three
- Question/load ID; missing fact or evidence; person/company responsible; due date; impact on planning; document reference when closed.
- Changes since the survey or previous plan
- Describe any change in plant, load, crane, rigging, location, ground, access, sequence or dates. Identify the affected drawings and who confirmed the change.
- Client information declaration
- Name, company, role, date and signature of the person providing the information. Confirm the attached information is current to the best of your knowledge and identify all estimates or unresolved points.
- Return and enquiry reference
- Send this saved PDF plus attachments to support@liftplannerpro.co.uk. Email subject: Lift planning enquiry - [project/site]. Enter your enquiry reference and preferred contact time.
The information declaration confirms the handover of data. It is not technical approval of the proposed lift or a substitute for the appointed person and site checks.
Scope agreement and approval route
Complete the commercial scope before work begins and agree the technical review route before the plan is issued for use.
- Fee and authorised scope
- £40 per hour plus VAT. Record agreed tasks, estimated hours, budget cap if agreed, quotation/PO reference and who may authorise additional time or revisions.
- Additional work and arrangements
- Record separately agreed site attendance/travel, surveys, specialist design/checking, expenses, delivery dates, revision allowance and payment terms. Do not assume these are included without agreement.
- Client authority to proceed
- Authorised name, company, role, signature and date. Identify the accepted written quotation/scope and any commercial conditions still outstanding.
- Technical review and checking
- Name the plan preparer, appointed person, independent checker if required, ground/temporary-works reviewer and client/site approver. State review sequence and the evidence each must accept.
- Issue and operational release
- Identify the final plan number/revision, approval record, briefing arrangements and person authorising the operation on site. List conditions that must be satisfied before work starts.
- Revision triggers
- Agree how altered load, crane duty/configuration, rigging, site levels, ground, weather limits, sequence or personnel are reported and reviewed before continuing.
LPP prepares the agreed planning deliverables for review. A completed intake or CAD simulation does not authorise lifting. The responsible competent people must verify the final arrangement and site conditions before operational release.